Download the Plugin

You must first download the plugin through the customer portal.

  1. Login to the customer portal.
  2. Locate and select the Downloads link in the system.
  3. Locate and click on the Edison folder.
  4. Locate and click on the Plugins folder.
  5. Locate and click on the Poway_Upgrade_X_X_X_XXXXX.zip file to download. Take note of the downloaded location.

Return to Top


Load the External Plugin

  1. Login to Edison.
  2. Select the Administration tab.
  3. Click on Miscellaneous and choose External Plugins.
  4. Click Add.
  5. Locate and select the Poway_Upgrade_X_X_X_XXXXX.zip plugin file from your local or network drive. Then, click Open.
  6. A notification window will appear. Click OK to install the plugin.
  7. After processes have run, notice the plugin status is Not loaded. Click Close.
  8. You must restart Edison for changes to take effect. Click OK and close the program.
  9. After restarting Edison, access external plugins to ensure the status has changed to loaded.

Return to Top


Run Reports

From the Reports tab, select the District report(s) you would like to run.

Inventory ReportsProduction ReportsOther Reports
  • Poway Food Transport Record Report
  • Poway Production Report
  • Poway Daily Cost Analysis
  • Poway Food Cost Index
  • Poway Non-Program Foods Sales
  • Poway Raw Food Cost


Return to Top


Establish a Scheduled Export Job

  1. From the Administration and Maintenance tab, select Advanced Setup. Then, choose Scheduled Jobs.
  2. Click the Add button.
  3. Enter the Scheduled Job information. Then, select Add Task to place tasks in the Scheduled Job.
    1. Description - Enter a description of the new Scheduled Job.
    2. Expected Period - Enter the Expected Period that the work schedule should be performed.
    3. Inactive - Select this option to make the Scheduled Job Inactive. 
  4. Select Run Report from the list of tasks. Then, click Ok.
  5. Configure the report task details. Then, click OK.
  6. In the Edit Scheduled Job window, click Ok.
  7. You may wish to run the scheduled job now. Select the Scheduled Job and click Run Now.
  8. A notification window will appear. Click Yes to confirm you wish to run the scheduled job.

Return to Top